University of Calgary Faculty of Law ABLawg.ca logo over mountains

Author: Nigel Bankes Page 54 of 89

Nigel Bankes is emeritus professor of law at the University of Calgary. Prior to his retirement in June 2021 Nigel held the chair in natural resources law in the Faculty of Law.

How much discretion does a regulator have to limit the recovery of a utility’s legal costs?

By: Nigel Bankes

PDF Version: How much discretion does a regulator have to limit the recovery of a utility’s legal costs?

Case Commented On: ATCO Gas and Pipelines Ltd v Alberta (Utilities Commission), 2014 ABCA 397

In this case the Court of Appeal confirmed that the Alberta Utilities Commission (AUC) has some level of discretion as to the extent to which it allows a regulated utility to recover its prudently incurred legal costs from its customers when that utility participates in hearings called by the AUC to consider generic issues of interest to all regulated utilities and their customers and shareholders. One member of the Court (Justice Peter Martin) thought that the Commission went too far in denying recovery in relation to one set of costs and would have sent that matter back to the Commission.

The decision is interesting because it involves the intersection between an adjudicator’s discretion to allow for the recovery of legal costs and the general principle that a utility ought to have the opportunity to recover all of its prudently incurred operating costs (including the legal costs associated with rate setting) through the tariff approved by the regulator. A decision that recognizes that a utility has prudently incurred certain costs but which then denies the utility even the opportunity to recover those costs will generally be unsupportable: BC Electric Railway Company v Public Utilities Commission, [1960] SCR 837. In this case however there were special considerations and thus while the majority found the Commission’s decision both reasonable and correct, the decision is not likely of broad application – a point that Chief Justice Fraser herself seems to acknowledge at paras 70 – 73. In particular, and notwithstanding other and rather more sweeping statements from the Chief Justice (see, for example para 106, quoted below, and paras 110 – 111), it is not likely that the decision can be applied in the more routine situation in which a utility incurs legal costs as part of preparing and presenting its general rate application (GRA) to the AUC for it to set just and reasonable rates. The AUC may still scrutinize those legal costs on prudence grounds (and see here in particular Justice Martin at para 171) to ensure that the utility is not gold-plating its costs (e.g. where it chooses to retain expensive outside counsel to undertake a task that could be more economically dealt with in-house) but it likely cannot say (even on a reasonableness standard of review) that the legal costs associated with preparing and presenting a GRA are not recoverable.

A Revised Aboriginal Consultation Direction issued to the Alberta Energy Regulator

By: Giorilyn Bruno and Nigel Bankes

PDF Version: A Revised Aboriginal Consultation Direction issued to the Alberta Energy Regulator

Direction and Decision Commented On: Energy Ministerial Order 105/2014 /  Environment and Sustainable Resource Development Ministerial Order 53/2014; Prosper Petroleum Ltd., 2014 ABAER 013

On October 31, 2014, the Minister of Energy and the Minister of Environment and Sustainable Resource Development (ESRD) by Order issued a revised Aboriginal Consultation Direction to the Alberta Energy Regulator (AER). The main purpose of this Direction is “to ensure that the AER considers and makes decisions in respect of energy applications in a manner that is consistent with the work of the Government of Alberta” in meeting its consultation obligations associated with the existing rights of Aboriginal people (Direction at 2). This is the second Ministerial Order issued under s. 67 of the Responsible Energy Development Act, SA 2012, c R-17.3 (REDA) and it repeals the previous one. In April we posted a blog commenting on the first Order (available here). This post provides an overview of the changes introduced by the new Direction, comments on its scope, and identifies some of the issues that have yet to be addressed.

Alberta Utilities Commission Approves the Proposed Sale of AltaLink’s Transmission Assets to the Berkshire Hathaway Group

By: Nigel Bankes

PDF Version: Alberta Utilities Commission Approves the Proposed Sale of AltaLink’s Transmission Assets to the Berkshire Hathaway Group

Decision Commented On: AUC Decision 2014-326, AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd et al, November 28, 2014

AltaLink owns significant transmission assets in Alberta. AltaLink in turn is owned by SNC Lavalin. SNC Lavalin wanted to divest itself of these assets and found a wiling purchaser in the form of the US based Berkshire Hathaway Group. The transaction however requires the approval of federal foreign investment and competition authorities (already in place) and of the Alberta Utilities Commission (AUC).

The AUC ‘s approval is required under the terms of s.102 of the Public Utilities Act, RSA 2000, c. P-45 (PUA) which provides as follows:

Unless authorized to do so by an order of the Commission, the owner of a public utility designated under section 101(1) shall not sell or make or permit to be made on its books a transfer of any share of its capital stock to a corporation, however incorporated, if the sale or transfer, in itself or in connection with previous sales or transfers, would result in the vesting in that corporation of more than 50% of the outstanding capital stock of the owner of the public utility.

Alberta Releases the Carbon Capture and Storage Quantification Protocol for Public Comment

By: Nigel Bankes

PDF Version: Alberta Releases the Carbon Capture and Storage Quantification Protocol for Public Comment

Document Commented On: Quantification Protocol for CO2 Capture and Permanent Storage in Deep Saline Aquifers, Version: DRAFT for public comment, November 2014 and associated commentary on changes made from the version released for technical review

The Government of Alberta (GoA) continues to make progress in putting together the legal and regulatory framework for commercial scale carbon capture and storage (CCS) projects in the province. Such a legal and regulatory framework needs to address four types of issues: (1) property issues including the ownership of pore space and a scheme for leasing or disposing of rights to pore space; (2) regulatory or permitting rules for reviewing the merits of particular projects and to establish the terms and conditions under which projects might proceed; (3) liability issues; and (4) greenhouse gas (GHG) accounting issues to ensure that CCS projects are fully integrated into regulatory approaches for managing greenhouse gas emissions – in the case of Alberta this means integrating CCS projects into the Specified Gas Emitter Regulation, Alta Reg 139/2007 (SGER).

The key elements of the province’s framework to date (with links to previous posts on the topic), are as follows:

Bill 1, Respecting Property Rights Act: A Damp Squib and a Good Thing Too

By: Nigel Bankes

PDF Version: Bill 1, Respecting Property Rights Act: A Damp Squib and a Good Thing Too

Bill Commented On: Bill 1: Respecting Property Rights Act

The good news about Bill 1 for those with communitarian views is that Bill 1 does not change the law of Alberta one iota. The bad news about Bill 1 for those of a more libertarian persuasion is that Bill 1 does not change the law of Alberta one iota.

Here is the entire text of Bill 1 from its bizarre preambular provisions to its single operative clause:

Preamble

WHEREAS private ownership of land is a fundamental element of Parliamentary democracy in Alberta;

WHEREAS the Alberta Bill of Rights recognizes and declares the right of the individual to the enjoyment of property and the right not to be deprived thereof except by due process of law;

WHEREAS the Government is committed to consulting with Albertans on legislation that impacts private property ownership;

WHEREAS the Land Assembly Project Area Act was enacted by the Legislature in 2009 and was amended in 2011 but has not been proclaimed in force; and

WHEREAS the repeal of the Land Assembly Project Area Act reaffirms the government’s commitment to respect individual property rights;

THEREFORE HER MAJESTY, by and with the advice and consent of the Legislative Assembly of Alberta, enacts as follows:

Land Assembly Project Area Act Repeal

  1. The Land Assembly Project Area Act, SA 2009 cL-2.5, is repealed.

This post addresses two questions. First, how is it that despite all the pomp and circumstance surrounding the introduction of this Bill, legally, it changes nothing? And second, why, at least in the opinion of this author, is that a good thing?

Page 54 of 89

Powered by WordPress & Theme by Anders Norén