By: Nigel Bankes and Heather Lilles
Case Commented On: Transocean Drilling UK Ltd v Providence Resources Plc [2016] EWCA Civ 372, [2016] 2 Lloyd’s Rep 51, 165 Con LR 1, [2016] BLR 360
This decision of the English Court of Appeal (Civil Division) which came out earlier this year (April 2016) is well worth reading both for its treatment of the exclusion of liability for consequential damages and also for its modern approach to the interpretation of commercial contracts. As recognized by the Court, the case “raises some interesting questions about the freedom of two commercial parties to determine the terms on which they wish to do business” (para 1).
Transocean Drilling UK Ltd (Transocean), the owner of a semi-submersible drilling rig, entered into a contract with Providence Resources Plc (Providence) to drill an offshore appraisal well for Providence. On 18 December 2011, Transocean suspended drilling operations due to a misalignment of part of the blow-out preventer. Transocean resumed operations on 2 February 2012. The trial judge determined that the delay was caused by Transocean’s breach of contract. There was no appeal on that point, but Transocean did appeal that part of the judge’s decision in which he allowed Providence to recover the ‘spread costs’ that it had incurred as a result of the delay. The ‘spread costs’ were described (at para 10) as “the costs of personnel, equipment and services contracted [by Providence] from third parties which were wasted as a result of the delay. Examples given by the judge are well logging, well testing and cementing, mud engineers and mud logging services, geological services, diving and ROV (remotely operated vehicle) services, weather services, directional drilling services, and running casings.” Continue reading