How much discretion does a regulator have to limit the recovery of a utility’s legal costs?

By: Nigel Bankes

PDF Version: How much discretion does a regulator have to limit the recovery of a utility’s legal costs?

Case Commented On: ATCO Gas and Pipelines Ltd v Alberta (Utilities Commission), 2014 ABCA 397

In this case the Court of Appeal confirmed that the Alberta Utilities Commission (AUC) has some level of discretion as to the extent to which it allows a regulated utility to recover its prudently incurred legal costs from its customers when that utility participates in hearings called by the AUC to consider generic issues of interest to all regulated utilities and their customers and shareholders. One member of the Court (Justice Peter Martin) thought that the Commission went too far in denying recovery in relation to one set of costs and would have sent that matter back to the Commission.

The decision is interesting because it involves the intersection between an adjudicator’s discretion to allow for the recovery of legal costs and the general principle that a utility ought to have the opportunity to recover all of its prudently incurred operating costs (including the legal costs associated with rate setting) through the tariff approved by the regulator. A decision that recognizes that a utility has prudently incurred certain costs but which then denies the utility even the opportunity to recover those costs will generally be unsupportable: BC Electric Railway Company v Public Utilities Commission, [1960] SCR 837. In this case however there were special considerations and thus while the majority found the Commission’s decision both reasonable and correct, the decision is not likely of broad application – a point that Chief Justice Fraser herself seems to acknowledge at paras 70 – 73. In particular, and notwithstanding other and rather more sweeping statements from the Chief Justice (see, for example para 106, quoted below, and paras 110 – 111), it is not likely that the decision can be applied in the more routine situation in which a utility incurs legal costs as part of preparing and presenting its general rate application (GRA) to the AUC for it to set just and reasonable rates. The AUC may still scrutinize those legal costs on prudence grounds (and see here in particular Justice Martin at para 171) to ensure that the utility is not gold-plating its costs (e.g. where it chooses to retain expensive outside counsel to undertake a task that could be more economically dealt with in-house) but it likely cannot say (even on a reasonableness standard of review) that the legal costs associated with preparing and presenting a GRA are not recoverable.

Alberta Utilities Commission Approves the Proposed Sale of AltaLink’s Transmission Assets to the Berkshire Hathaway Group

By: Nigel Bankes

PDF Version: Alberta Utilities Commission Approves the Proposed Sale of AltaLink’s Transmission Assets to the Berkshire Hathaway Group

Decision Commented On: AUC Decision 2014-326, AltaLink Investment Management Ltd. and SNC Lavalin Transmission Ltd et al, November 28, 2014

AltaLink owns significant transmission assets in Alberta. AltaLink in turn is owned by SNC Lavalin. SNC Lavalin wanted to divest itself of these assets and found a wiling purchaser in the form of the US based Berkshire Hathaway Group. The transaction however requires the approval of federal foreign investment and competition authorities (already in place) and of the Alberta Utilities Commission (AUC).

The AUC ‘s approval is required under the terms of s.102 of the Public Utilities Act, RSA 2000, c. P-45 (PUA) which provides as follows:

Unless authorized to do so by an order of the Commission, the owner of a public utility designated under section 101(1) shall not sell or make or permit to be made on its books a transfer of any share of its capital stock to a corporation, however incorporated, if the sale or transfer, in itself or in connection with previous sales or transfers, would result in the vesting in that corporation of more than 50% of the outstanding capital stock of the owner of the public utility.