Bill 27: Financial Support for Renewable Electricity

By: Nigel Bankes

PDF Version: Bill 27: Financial Support for Renewable Electricity

Legislation Commented On: Bill 27, Renewable Electricity Act

Report Commented On: AESO, Renewable Electricity Program, Recommendations, dated May 2016, publicly released November 3, 2016

Press Release Commented On: Government of Alberta, Renewable electricity plan to create jobs, spur investment, November 3, 2016

Alberta’s Climate Leadership Plan (CLP) of November 2015 has four key planks:

  1. Phasing out emissions from coal-generated electricity and developing more renewable energy
  2. Implementing a new carbon price on greenhouse gas emissions
  3. A legislated oil sands emission limit
  4. Employing a new methane emission reduction plan

The government introduced legislation to implement an economy-wide carbon price in June (the Climate Leadership Implementation Act) and in the resumed session this fall (2016) it introduced first of all Bill 25: The Oil Sands Emission Limit Act to implement the third objective, a legislated oil sands emission limit (I commented on Bill 25 here) followed now by Bill 27, the Renewable Electricity Act to implement the second half of the first plank – developing more renewable energy. We have yet to see the detailed plans for phasing out coal generation.

Oil Sands Emission Limit Legislation: A Real Commitment or Kicking It Down the Road?

By: Nigel Bankes

PDF Version: Oil Sands Emission Limit Legislation: A Real Commitment or Kicking It Down the Road?

Legislation Commented On: Bill 25: The Oil Sands Emission Limit Act

Alberta’s Climate Leadership Plan has four key planks:

  1. Phasing out emissions from coal-generated electricity and developing more renewable energy
  2. Implementing a new carbon price on greenhouse gas emissions
  3. A legislated oil sands emission limit
  4. Employing a new methane emission reduction plan

The province introduced legislation to implement an economy-wide carbon price in June (the Climate Leadership Implementation Act) and in the resumed session this fall (2016) it has introduced Bill 25: The Oil Sands Emission Limit Act to implement the third objective, a legislated oil sands emission limit. This was not something that the Leach Report had recommended but here is what the Government said in making this commitment:

Attorney General Argues That Backdoor Amendment to PPAs was Unlawful

By: Nigel Bankes

PDF Version: Attorney General Argues That Backdoor Amendment to PPAs was Unlawful

Matter Commented On: Originating Application for Declaratory Relief and Judicial Review, filed by the Attorney General, July 25, 2016

The origins of the Power Purchase Arrangements (PPAs) “termination” saga are discussed in detail in a previous post and readers may wish to refer to that post for the necessary background. In an interesting development the Attorney General has commenced an application seeking a declaration that the amendments that were made to the PPAs after the public review process conducted by the then Alberta Energy and Utilities Board (AEUB) had concluded are unlawful. The crucial amendment was to a clause in the PPA which allows the buyer to transfer responsibility for the PPA to the Balancing Pool when a change of law makes the PPA not just unprofitable but “more unprofitable”.

Will the Flurry of New Wind Energy Projects Face a Storm of Opposition?

By: Jeremy Barretto

PDF Version: Will the Flurry of New Wind Energy Projects Face a Storm of Opposition?

Decision Commented On: AUC Decision 3329-D01-2016, E.ON Climate & Renewables Canada Ltd., Applications for the Construction and Operation of the Grizzly Bear Creek Wind Power Project, May 19, 2016.

According to Alberta’s Climate Leadership Plan, renewable sources are expected to account for up to 30% of the province’s electricity generation by 2030—approximately triple today’s renewable generation. The provincial government is developing a competitive process to bring new renewable generation capacity to the grid, based on reports from an expert panel and the Alberta Electric System Operator. The first competition will be in Q4 2016.

As I’ve previously written, wind projects will likely obtain most government financial incentives, provided that such incentives are offered through a competitive auction for utility-scale renewable energy projects. That’s because upfront costs for wind energy projects are typically lower than other forms of renewable energy. The rapid development of wind energy in Ontario and recent Alberta decisions foreshadow potential vigorous opposition, and key process differences, for the anticipated flurry of new wind energy projects.

The Termination of Power Purchase Arrangements in Alberta: What is the Legal Position and What are the Implications of Termination?

By: Nigel Bankes

PDF Version: The Termination of Power Purchase Arrangements in Alberta: What is the Legal Position and What are the Implications of Termination?

Case Commented On: The decisions of various buyers to “terminate” their interests in power purchase arrangements (PPAs)

In December 2015, Enmax announced that it was “terminating” its interest in a power purchase arrangement (PPA) with the owner of the Battle River 5 coal plant subject to the PPA (see Enmax terminates unprofitable-coal-fired electricity contract). That was followed this month (March 2016) with announcements from TransCanada Energy and ASTC Power Partnership (a partnership of Trans Canada Energy and AltaGas Pipelines) that they too had given notice to terminate and would be walking away from their obligations as buyers under PPAs relating to Sheerness and Sundance A and B. In announcing its decision, TransCanada indicated that it was doing so because “Unprofitable market conditions are expected to continue as costs related to CO2 emissions have increased and they are forecast to continue to increase over the remaining term of the PPA agreements.” It is generally understood that reference to “costs related to CO2 emissions” is a reference to the emissions penalty imposed by the Specified Gas Emitter Regulation (SGER), Alta Reg 139/2007. This Regulation, first introduced in 2007, requires regulated emitters (including owners of coal fired generating plants) to achieve improvements in emissions intensity at their facilities (or purchase offsets or emissions performance credits) failing which these emitters must pay into the Climate Change and Emission Management Fund. The emissions intensity target was originally set at 12% over the original baseline for the facility and the fund contribution at $15 a tonne (payable only for emissions in excess of the emissions intensity target for the facility). While the previous government dithered and procrastinated on changes to the intensity target and changes to the level of fund contribution (indeed the previous government extended the sunset provision in the regulation twice), the Notley government grasped the nettle, and, in June 2015 announced, as an interim step in the development of a more comprehensive climate change policy, that regulated emitters will be required to achieve an emissions intensity target of 15% in 2016 and 20% in 2017, while the compliance price for excess emissions will rise from $20 per tonne in 2016 to $30 per tonne in 2017. Those developments are discussed in an earlier post here.